Building Adjudication Victoria Inc
Home | About BAV | Adjudication | Claimants | Respondents | Fact Sheets | Forms | Apply to BAV
   
BAV acknowledges the kind permission of the Building Commission in allowing the reproduction of the following material.

What is an adjudication?
What is an Authorised Nominating Authority (ANA)?
What is an Adjudicator?
What does adjudication cost?
How long does adjudication take?
How does an adjudicator make a determination?
What does the adjudicator determine?
What happens after the adjudicator has made a decision?
What if the respondent doesn't pay an adjudicated amount?
What is a 'relevant principal'?
Enforcing an adjudicator's determination
What is an adjudication certificate?
Can an adjudicator's determination be reviewed?
Judicial review of adjudication determinations
Making a complaint about an adjudication
What happens if I don't pay the claimed amount?
 

What is an adjudication?

Adjudication is a process created by the Building and Construction Industry Security of Payment Act 2002 to resolve a disputed claim for payment due under a construction contract. It can help resolve payment disputes quickly, fairly and at less cost than going to court.

An independent adjudicator receives written submissions from both sides of the payment dispute, conducts inspections or conferences where necessary, and decides the amount, if any, which is due in respect of a progress payment claimed under the Act. The adjudicator makes the determination within 10 business days. This time may be extended to 15 business days if the claimant agrees. The decision is interim, and does not affect the parties' substantive rights and obligations under the contract.

Top of page

What is an Authorised Nominating Authority (ANA)?

An ANA is an organisation that has been authorised by the Building Commission to nominate adjudicators under the Act. Before authorising an ANA, the Commission must have regard to guidelines issued by the Minister. In carrying out their functions, ANAs must comply with the Act, the Regulations and Conditions of Authorisation. A breach of any requirement or condition may affect the authorisation of the ANA. Authorisation is generally for a period of three years.

Top of page

What is an Adjudicator?

An adjudicator must have relevant educational qualifications and substantial experience in the administration, management and supervision of construction contracts or in dispute resolution relating to construction contracts. ANAs are required, as a condition of authorisation, to ensure that the adjudicators they nominate meet minimum core competencies and comply with professional standards of conduct.

The Adjudicator Core Competencies and Adjudicator Standards of Conduct that apply to all adjudicators nominated under the Act are available.

In conducting an adjudication, the adjudicator must be fair and act independently. An adjudicator cannot accept an adjudication application if doing so would create any actual or likely conflict of interest, or any perception of conflict of interest or bias on their part.

Any complaints about an adjudicator should be referred to the ANA.

Top of page

What does adjudication cost?

There are two parts to the adjudication cost: the ANA's fees and the adjudicator's fees and expenses.

Any costs of the adjudication apart from the fees of ANAs and adjudicators are borne by the parties that incur them.  The adjudicator does not have power to make any determination in relation to these costs. 

  • ANA's fees

The ANA may charge an application fee and fees for services in connection with the application. The fees amongst the different ANAs may vary.  ANAs are required to provide information about the fees they charge. 

  • Adjudicator's fees and expenses

Adjudicators' fees may vary, depending on the nature and complexity of the issues in dispute, the time required and the expertise of the adjudicator.  Generally, adjudicators charge an hourly rate. They may also charge for expenses associated with the adjudication such as the cost of visiting the construction site.  Before accepting an adjudicator, claimants may inquire about their fees.

The parties to an adjudication are each liable to contribute to the adjudicator's fees and expenses in equal proportions, or in such proportions as the adjudicator may determine. 

  • Adjudicator's entitlement in relation to fees

An adjudicator is entitled to be paid reasonable fees and expenses having regard to the work that he or she has done.  This may include an amount for work done on a matter which is withdrawn or resolved by the parties.  They may also charge for expenses associated with the adjudication such as the cost of visiting the construction site. 

An adjudicator is not entitled to be paid for work done where he or she fails to make a decision within the time allowed.

An adjudicator is entitled to refuse to communicate the decision until his or her fees and expenses have been paid.  If a party refuses to pay his or her share, the other party may elect to pay both parties' shares to enable the adjudication determination to be released.  If the other party pays, the adjudicator will add that unpaid share amount to the adjudicated amount. 

See Fact Sheet 6: Adjudication

Top of page

How long does adjudication take?

An adjudicator must be appointed by an ANA.  After receiving an adjudication application, the ANA is required to refer it to an adjudicator as soon as practicable.  An adjudicator must notify the parties of his or her acceptance of the notification within 4 business days after an adjudication application is made, or the claimant can withdraw it and make a new one. 

The respondent has up to 5 business days to give the adjudicator a written response but only if they have given the claimant a payment schedule. 

After agreeing to adjudicate, the adjudicator has 10 business days (or 15 if the claimant agrees) to reach a decision. 

See Fact Sheet 6: Adjudication

Top of page

How does an adjudicator make a determination?

In reaching a determination, the adjudicator must consider only the following matters:

  • The Act and regulations
  • The construction contract from which the application arose
  • The payment claim to which the application relates, together with all submissions
        (including relevant documentation) the claimant has relied upon
  • The payment schedule (if any) to which the application relates, together with all submissions
        (including relevant documentation) that the respondent has relied upon and
  • The results of any inspection carried out of any matter to which the claim relates.

Top of page

What does the adjudicator determine?

At the completion of the process, the adjudicator determines the amount (if any) that the respondent must pay the claimant and when it is to be paid.

The adjudicator's decision is in writing and will include the reasons for the decision and the basis on which any amount or date has been decided

Top of page

What happens after the adjudicator has made a decision?

If the adjudicator determines the respondent is to pay an amount to the claimant, the respondent must pay the adjudicated amount within 5 business days of receiving the adjudicator's decision, or the date upon which the adjudicator determines the amount becomes payable, whichever is the later.

See Fact Sheet 11: If the respondent doesn't pay

Top of page

What if the respondent doesn't pay an adjudicated amount?

If the respondent fails to pay an adjudicated amount on time, the claimant has the following options:

  • Go to court to recover the adjudicated amount

The claimant can recover the adjudicated amount by filing an adjudication certificate and supporting affidavit in the appropriate court.  The adjudication certificate is available from the Authorised Nominating Authority (ANA) to which the adjudication application was made.  It sets out the names of the parties, the amount payable and the date on which it was due to be paid.  The affidavit attests to the fact that the amount is still outstanding.  The adjudicated amount will become a judgment debt, which is enforceable in the same way as any court judgment.  Fees will be payable to the ANA for the adjudication certificate and to the court for registration of the debt. 

  • Recovery from the principal

If the adjudicated amount is for work, goods or services that are incidental to or part of a contract between the respondent and a third party (the principal), the claimant may recover the adjudicated amount from the principal.  This option is not available in relation to a domestic building contract with a building owner, unless the building owner is in the business of building residences.

To recover payment from the principal, the claimant must obtain an order from a court for the adjudicated amount.  The court will issue a Debt Certificate, which must be served on the principal with a Notice of Claim.  The Notice of Claim and Debt Certificate must be in the prescribed forms, which are set out in the Building and Construction Industry Security of Payment Regulations 2003.

  • Other actions

Until the debt is paid, the claimant retains the right to suspend work or the supply of goods and services and to exercise a lien over unfixed plant and materials.

See Fact Sheet 11: If the respondent doesn't pay

Top of page

What is a 'relevant principal'?

The adjudicator must notify any relevant principal of an adjudication application.

A relevant principal is any person who has engaged the respondent under a contract to provide construction work, goods or services, if the work that the claimant has done or the goods or services that the claimant has supplied under contract to the respondent is, or is part of or incidental to, the construction work, goods or services that the respondent was engaged to carry out or supply. 

This does not include the principal in a domestic building contract to which the Act doesn't apply. 

For more information about this exemption see Fact Sheet 1: The Security of Payment scheme

Top of page

Enforcing an adjudicator's determination

Where a respondent fails to pay an adjudicated amount by the due date, the claimant can recover the adjudicated amount by filing an adjudication certificate and supporting affidavit in the appropriate court. 

The adjudication certificate is provided by the Authorised Nominating Authority (ANA) to which the adjudication application was made.  It sets out the names of the parties, the amount payable and the date on which it was due to be paid. 

The respondent may apply to the court to have the judgment set aside, however in these proceedings, the respondent is not entitled to:

  • bring any cross-claim against the person who brought the proceedings
  • raise any defence in relation to matters arising under the construction contract
  • challenge the adjudicator's or review adjudicator's determination.

Defences and cross claims under the contract may be decided at separate hearing. 

The adjudicated amount will become a judgment debt, which is enforceable in the same way as any court judgment.  Fees will be payable to the court for filing the claim or registration of the debt.  All enforcement methods attract court fees.

The courts of competent jurisdiction are the Magistrates' Court of Victoria, the County Court of Victoria and the Supreme Court of Victoria.  The claimant will select the appropriate court according to the amount of the claim. 

For more information, contact the relevant court.

Top of page

What is an adjudication certificate?

The adjudication certificate is provided by the Authorised Nominating Authority (ANA) to which the adjudication application was made.  It sets out the names of the parties, the amount payable and the date on which it was due to be paid.  Where a respondent fails to pay an adjudicated amount by the due date, the claimant can recover the adjudicated amount by filing an adjudication certificate and supporting affidavit in the appropriate court.

Top of page

Can an adjudicator's determination be reviewed?

The adjudication process established by the Act is intended to provide a quick and inexpensive way to resolve payment disputes arising under construction contracts.  In support of this aim, adjudicator's decisions are generally not reviewable. 

However, an adjudicator's determination may be reviewed by another adjudicator in limited circumstances.  The adjudication review process is available to both parties.

A determination may be reviewed only where the contract was entered on or after 30 March 2007, and the adjudicated amount exceeds $100,000.

The grounds for review are limited.  A respondent may seek review of a determination on the ground that the adjudicator wrongly included in the determination amounts which are 'excluded amounts'.  A claimant may seek review of a determination on the ground that the adjudicator failed to include in the determination an amount or amounts wrongly identified as 'excluded amounts'.

See Fact Sheet 7: Adjudication review

Top of page

Judicial review of adjudication determinations

If an adjudicator acts in good faith and complies with the basic and essential requirements of the Act their determination will be enforced by the courts. 

An adjudicator's determination may be challenged in the courts only in limited circumstances, for example:

  • The adjudicator has failed to comply with the basic and essential requirements of the Act
  • An adjudicator took into account an amount excluded by the Act
  • The adjudicator has denied natural justice to a party
  • The adjudication determination is obtained by fraud in which the adjudicator is complicit.

If a claimant commences proceedings to recover any unpaid amount under the Act, a respondent may not make any cross-claim for damages for breach of contract or any other cross-claim.  A respondent who is dissatisfied with the adjudicator's decision may bring separate proceedings for repayment of any alleged overpayment, or as part of the final determination of issues under the contract.

Top of page

Making a complaint about an adjudication

All complaints regarding the ANA process or any conduct by an adjudicator, officer or personnel of the ANA should first be referred to the ANA. 

The Conditions of Authorisation require ANAs to establish complaints procedures which address complaints relating to any process arising out of the Act, including:

  • any conduct by any officer or personnel of the ANA
  • any conduct by an adjudicator nominated by the ANA, or
  • any other relevant matter concerning the ANA.

The ANA must make any person involved in the adjudication process aware of their complaints procedures.  They are required to report to the Building Commission about any complaints they receive about the adjudicators they nominate.

All ANAs must comply with the Act, the Regulations and the ANA Conditions of Authorisation.  A breach of any requirement or condition may affect the authorisation of the ANA.

What happens if I don't pay the claimed amount?

The Act requires a respondent who receives a valid payment claim to pay the amount claimed in full by the due date or give the claimant a payment schedule within 10 days.  If the respondent does not do one of these things within the required time, they become liable for the amount claimed.

The claimant may apply for adjudication or go to court to recover the unpaid amount.  The claimant may also exercise a lien in respect of the unpaid amount over any unfixed plant or materials they have supplied to you for use in connection with carrying out construction work under the contract.  They may also suspend works, or the supply of goods and services under the contract, until the amount payable has been paid. 

A 'paid when paid' provision in a construction contract has no effect.  The claimant cannot be required to wait until the respondent is paid by someone else under another contract. 

The claimant also has these options if you:

  • Provide a payment schedule and the scheduled amount is less than the claimed amount, or
  • Provide a payment schedule but do not pay the scheduled amount by the due date.

Top of page

 

 

Building Adjudication Victoria Inc.

Level 3, 296 Collins St.
Melbourne Vic. 3000

t : 03 9663 4722
f : 03 9663 4799
bav @ rodlaw.com.au