Building Adjudication Victoria Inc
Home | About BAV | Adjudication | Claimants | Respondents | Fact Sheets | Forms | Apply to BAV
   
BAV
BAV acknowledges the kind permission of the Building Commission in allowing the reproduction of the following material.
Claimants - contracts after 30 March 2007

Who can make a claim under the Security of Payment Scheme?
What types of work or services does the Act apply to?
What is a payment claim?
What is the 'Security of Payment Statement'?
What types of payments can be claimed?
What is a claimable variation?
What is an excluded amount?
When should I make a payment claim?
How do I calculate my payment claim?
Is interest payable on an unpaid progress payment?
How do I serve a payment claim?
What happens after I serve my payment claim?
What happens if the respondent does not provide a payment schedule?
When can the claimant apply for adjudication?
How does the claimant apply for adjudication?
What is an Authorised Nominating Authority (ANA)?
What should be included in an adjudication application?
How do I serve an adjudication application?
What happens after I lodge an adjudication application?
The right to suspend work or the supply of goods and services
Recovery from the principal
Can an adjudicator's determination be reviewed?

Who can make a claim under the Security of Payment Scheme?

A person who has carried out work or supplied goods and services under a construction contract in Victoria (the claimant) can claim progress payments by giving a 'payment claim' to the relevant contractor, purchaser or client (the respondent). 

The contract may be written, oral or a combination of both. 

A Security of Payment claim can be made by:

  • Contractors
  • Subcontractors
  • Suppliers of material or building components in construction work
  • Architects, engineers or others providing building advice.

Go to Top

What types of work or services does the Act apply to?

The Act applies to the following types of work:

  • Residential and non-residential building
  • Civil engineering
  • Professional services (e.g. architecture, design, surveying)
  • Maintenance
  • Mechanical/air conditioning
  • Plumbing
  • Demolition
  • Hire of plant and equipment
  • Supply of building materials
  • Electrical
  • Landscaping.

The Act does not apply to contracts to carry out domestic building work with a building owner unless the building owner is in the business of building residences and the contract is entered into in the course of or in connection with that business. These contracts come under the Domestic Building Contracts Act 1995.  However, contracts between a home owner's building contractor and any sub-contractor or supplier are covered.

Go to Top

What is a payment claim?

A payment claim is a claim for a progress payment which is made under the Act.  To be valid, the payment claim must specify the work, goods or services supplied and the amount claimed and state that it is made under the Building and Construction Industry Security of Payment Act 2002

A client or purchaser who receives a payment claim from a contractor must either pay the contractor the claimed amount when it's due, or give them a payment schedule within 10 business days (or less if the contract says so).

See Fact Sheet 3: Making a payment claim

Go to Top

What is the 'Security of Payment Statement'?

To be valid under the Act, a payment claim must say: 'This is a payment claim under the Building and Construction Industry Security of Payment Act 2002'.  This notifies the respondent that the claim is made under the Act.

Go to Top

What types of payments can be claimed?

Claims may be made under the Act for 'progress payments' for work done or supplies made since a date determined by the contract or under the Act.

This includes final, single and milestone payments. 

The Act specifies which variations may be claimed in a payment claim - these are 'claimable variations'.

The Act expressly excludes certain amounts from being claimed in a payment claim.  These are called 'excluded amounts'.

See Fact Sheet 3: Making a payment claim

Go to Top

What is a claimable variation?

All agreed variations and some disputed variations may be claimed in a payment claim.

If the original contract value is less than $150,000, the Act applies to all claims for disputed variations.

If the original contract value is between $150,000 and $5 million, the Act applies to claims for disputed variations up to 10% of the original contract sum.

If the original contract value is more than $5 million, disputed variations must be resolved by the dispute resolution methods specified in the contract.

See Fact Sheet 4: Claimable variations and excluded amounts

Go to Top

What is an excluded amount?

The Act expressly excludes certain amounts from being claimed in a payment claim.  These are called 'excluded amounts'.  An adjudicator may not consider an excluded amount in a payment claim, and their determination will be void to the extent they do so. 

  • An excluded amount is
  • Any amount of the contract that is not a claimable variation as described above
  • Compensation due to the happening of an event, such as latent conditions, time related costs and changes in regulatory requirements
  • Damages for breach of the contract or for any other reason related to the contract
  • Any claim arising at law other than under the contract.

While a dispute about an excluded amount cannot be the subject of a payment claim under the Act, it may still be resolved in accordance with any dispute resolution provisions in the contract or by going to court.

See Fact Sheet 4: Claimable variations and excluded amounts

Go to Top

When should I make a payment claim?

A payment claim must be served within 3 months after the reference date, or within the period specified in the contract - whichever is later.

A reference date is the date on which a claim may be made.  If the contract does not specify reference dates, the Act provides for them as follows:

Progress payments - 20 business days after the work was first carried out or goods and services were first provided.  Subsequent payment claims may then be made every 20 business days until the job is completed.

Single or one-off payments - The day after the work was last carried out or the goods or services were last supplied under the contract.

Final payments - The day after the end of any period under the contract for rectifying defects or omissions or the day after the final certificate is issued.  If neither of these applies, the reference date is the day after the work was last carried out or the goods or services were last supplied under the contract.

Go to Top

How do I calculate my payment claim?

The payment claim must take into account the contract price for the construction work or supply of related goods and services, any other rates or prices set out in the contract and the estimated cost of rectifying any defect.  It may include claimable variations but not excluded amounts. 

The progress payment becomes due on the date specified by the contract; or if the contract does not specify, 10 business days after the payment claim is made.

Go to Top

Is interest payable on an unpaid progress payment?

Interest is payable on the unpaid amount of a progress payment at the rate specified under the construction contract, or at the rate fixed under section 2 of the Penalty Interest Rates Act 1983, whichever is greater.

Go to Top

How do I serve a payment claim?

A document may be served under the Act in one of the following ways:

  1. Delivered in person. It is 'served' when the respondent receives it.
  2. Lodged during business hours at the respondent's ordinary place of business. It is 'served' when it is received at that address.
  3. Sent by post to the respondent's ordinary place of business. It is 'served' 2 business days after the day it is posted.
  4. Faxed to the respondent's ordinary place of business. It is 'served' at the time it is received unless it is received after 4pm. If it is received after 4pm, it is taken to have been 'served' on the next business day.
  5. Provided in any other manner specified in the contract.

Go to Top

What happens after I serve my payment claim?

Under the Act, the respondent may respond to a payment claim in one of 2 ways:

  • Pay the amount claimed in full, on or before the due date. 
  • Give you a payment schedule within 10 days (or sooner, if the contract sets a shorter deadline) setting out what they are willing to pay and why it is any different from the amount claimed.

A 'paid when paid' provision in a construction contract has no effect.  You cannot be required to wait until the respondent is paid by someone else under another contract.

Go to Top

What happens if the respondent does not provide a payment schedule?

A respondent who does not provide a payment schedule on time is liable to pay the full amount claimed.  If it is not paid on time, the claimant may go to court to recover the full amount as a debt or apply for adjudication.  The respondent may be charged interest on the unpaid claimed amount. 

The claimant is also entitled to suspend work or cease supplying related goods and services under the contract until the amount payable has been paid.  The claimant must give the respondent 3 days' written warning of the suspension.  A claimant who exercises this right in accordance with the Act is not liable for any loss or expense suffered by the respondent as a consequence of the suspension. 

The claimant has the right to exercise a lien in respect of the unpaid amount over any unfixed plant or materials that the claimant has provided in connection with carrying out construction work for the respondent.  This means the respondent may not fix, remove, sell or otherwise deal with the plant or materials until the claimant is paid the outstanding amount.  The claimant must serve a Notice of Lien on the respondent in a particular form.  The form is prescribed in the Building and Construction Industry Security of Payment Regulations 2003

See Fact Sheet 12: Lien over unfixed plant and materials

Go to Top

When can the claimant apply for adjudication?

Claimants may apply for adjudication when they have served a payment claim on a respondent under the Act and one of the following circumstances has arisen:

  • The respondent provides a payment schedule which shows that the amount that they propose to pay (the 'scheduled amount') is less than the amount claimed on the payment claim (the 'claimed amount').
  • The claimant can apply for adjudication under section 18(1)(a)(i) of the Act.
  • The claimant has 10 business days after receiving the payment schedule to apply.
  • The respondent provides a payment schedule but does not pay any or all of the 'scheduled amount' when it is due.
  • The claimant can apply for adjudication under section 18(1)(a)(ii) of the Act.
  • The claimant has 10 business days after the due date for payment to apply.
  • The respondent fails to provide a payment schedule or pay any or all of the 'claimed amount' when it is due.
  • The claimant can apply for adjudication under section 18(1)(b) of the Act.
  • The claimant has 10 business days after the due date for payment to notify the respondent that they intend to apply and that the respondent has 2 business days to provide a payment schedule.  After notifying the respondent, the claimant has a further 7 business days to lodge the application - whether or not the respondent provides a payment schedule.

Go to Top

How does the claimant apply for adjudication?

The claimant applies for adjudication by lodging an application with an Authorised Nominating Authority (ANA) such as BAV, which then nominates the adjudicator. 

Go to Top

What is an Authorised Nominating Authority (ANA)?

An ANA is an organisation that has been authorised by the Building Commission to nominate adjudicators under the Act.  Before authorising an ANA, the Commission must have regard to guidelines issued by the Minister.  In carrying out their functions, ANAs must comply with the Act, the Regulations and Conditions of Authorisation.  A breach of any requirement or condition may affect the authorisation of the ANA.  Authorisation is generally for a period of three years. 

Go to Top

What should be included in an adjudication application?

The application must be in writing and identify the payment claim and the payment schedule to which it relates.  It should be lodged with any application fee charged by the ANA.  The claimant may make submissions that are relevant to the application, including the reasons for disagreeing with the payment schedule, and should attach copies of documents that they want the adjudicator to take into consideration.

There is no prescribed form for an adjudication application.  The Building Commission has prepared a sample adjudication application form which can be filled in or used as a guide.

Go to Top

How do I serve an adjudication application?

A document may be served under the Act in one of the following ways:

  1. Delivered in person. It is 'served' when the respondent receives it.
  2. Lodged during business hours at the respondent's ordinary place of business. It is 'served' when it is received at that address.
  3. Sent by post to the respondent's ordinary place of business. It is 'served' 2 business days after the day it is posted.
  4. Faxed to the respondent's ordinary place of business. It is 'served' at the time it is received unless it is received after 4pm. If it is received after 4pm, it is taken to have been 'served' on the next business day.
  5. Provided in any other manner specified in the contract.

Go to Top

What happens after I lodge an adjudication application?

The ANA will refer the adjudication application to an adjudicator as soon as practicable. The parties will be notified within 4 business days that an adjudicator has accepted the application. If parties have not been notified by then, the claimant may withdraw the application (by notifying the ANA in writing) and make a new one.

A copy of the application must be given to the respondent.  The respondent has up to 5 business days to give the adjudicator a written response but only if they have given the claimant a payment schedule.  The claimant receives a copy of the adjudication response.  After agreeing to adjudicate, the adjudicator has 10 business days (or 15 if the claimant agrees) to reach a decision.

Go to Top

The right to suspend work or the supply of goods and services

The claimant is entitled to suspend work or cease supplying related goods and services under the contract until the amount payable has been paid, if the respondent:

  • fails to pay in accordance with the payment schedule or
  • does not provide a payment schedule and does not pay the claimed amount by the due date.

The claimant must give the respondent 3 business days' written notice of the suspension.  The notice must state that it is made under the Act.  A claimant who exercises this right in accordance right in accordance with the Act is not liable for any loss or expense suffered by the respondent as a consequence of the suspension.  The right exists until the amount payable has been paid.

Go to Top

Recovery from the principal

If the adjudicated amount is for work, goods or services that are incidental to or part of a contract between the respondent and a third party (the principal), the claimant may recover the adjudicated amount from the principal. 

The claimant must obtain an order from a court for the adjudicated amount.  The court will issue a Debt Certificate, which must be served on the principal with a Notice of Claim.  The Notice of Claim and Debt Certificate must be in the prescribed forms, which are set out in the Building and Construction Industry Security of Payment Regulations 2003. 

Service of the Notice of Claim assigns to the claimant the debt owed by the principal to the respondent.  The principal must then pay the claimant the money that the principal owes the respondent until the debt is discharged or the principal is no longer required to pay the respondent.  If the principal fails to make the payment as required, the claimant may sue for recovery of the debt. 

This option is not available where the principal is a homeowner, unless the homeowner is in the business of building residences and the contract is entered into in the course of or in connection with that business.

Go to Top

Can an adjudicator's determination be reviewed?

The adjudication process established by the Act is intended to provide a quick and inexpensive way to resolve payment disputes arising under construction contracts.  In support of this aim, adjudicator's decisions are generally not reviewable.  However, an adjudicator's determination may be reviewed by another adjudicator in limited circumstances.  This process is available to both parties.

A determination may be reviewed only where the contract was entered on or after 30 March 2007, and the adjudicated amount exceeds $100,000.

The grounds for review are limited.  A respondent may seek review of a determination on the ground that the adjudicator wrongly included in the determination amounts which are 'excluded amounts'.  A claimant may seek review of a determination on the ground that the adjudicator failed to include in the determination an amount or amounts wrongly identified as 'excluded amounts'.

See Fact Sheet 7: Adjudication review

Go to Top

 

 

Building Adjudication Victoria Inc.

Level 3, 296 Collins St.
Melbourne Vic. 3000

t : 03 9663 4722
f : 03 9663 4799
bav @ rodlaw.com.au