Building Adjudication Victoria Inc
Home | About BAV | Adjudication | Claimants | Respondents | Fact Sheets | Forms | Apply to BAV
   
BAV acknowledges the kind permission of the Building Commission in allowing the reproduction of the following material.

How should I respond to a payment claim?
What can be claimed in a payment claim?
What is a claimable variation?
What is an excluded amount?
What happens if I don't pay the claimed amount?
What happens if I don't submit a payment schedule?
What should be included in a payment schedule?
How do I serve a payment schedule?
What if the claimant disputes the payment schedule?
When can the claimant apply for adjudication?
What do I do if I receive an adjudication application?
What should be included in an adjudication response?
What happens if I don't pay an adjudicated amount?
Can I ask for review of the adjudication?
How do I apply for adjudication review?
Can a claimant suspend work?
When can an adjudicated amount be recovered from the contract principal?
What is a 'relevant principal'?

How should I respond to a payment claim?

You may respond to a payment claim in one of 2 ways.

  • If you agree with the payment claim, pay the amount claimed in full, on or before the due date.
  • If you do not agree to pay the full amount by the due date, give the claimant a payment schedule within 10 days (or sooner, if the contract sets a shorter deadline) setting out what you are willing to pay and why it is any different from the amount claimed.

A 'paid when paid' provision in a construction contract has no effect.  The claimant cannot be required to wait until you are paid by someone else under another contract before being entitled to claim the money owed to them.

Top of page

What can be claimed in a payment claim?

All payments for the original contract sum may be claimed in a payment claim.  The payment claim may also include any variation agreed to by the parties to the contract by which the contract price, or any other rate or price set out in the contract is to be adjusted by a specific amount.

Variations which may be claimed are called 'claimable variations'.  These include all agreed variations and some disputed variations.

A progress payment may include final payments, single payments and milestone payments.

Claims for damages, delay costs and latent conditions are excluded.

See Fact Sheet 4: Claimable variations and excluded amounts

Top of page

What is a claimable variation?

All agreed variations and some disputed variations may be claimed in a payment claim.

If the original contract value is less than $150,000, the Act applies to all claims for disputed variations.

If the original contract value is between $150,000 and $5 million, the Act applies to claims for disputed variations up to 10% of the original contract sum.

If the original contract value is more than $5 million, disputed variations must be resolved by the dispute resolution methods specified in the contract.

See Fact Sheet 4: Claimable variations and excluded amounts

Top of page

What is an excluded amount?

The Act expressly excludes certain amounts from being claimed in a payment claim.  These are called 'excluded amounts'.  An adjudicator may not consider an excluded amount in a payment claim, and their determination will be void to the extent they do so. 

An excluded amount is

  • Any amount of the contract that is not a claimable variation as described above
  • Compensation due to the happening of an event, such as latent conditions, time related costs and changes in regulatory requirements
  • Damages for breach of the contract or for any other reason related to the contract
  • Any claim arising at law other than under the contract.

While a dispute about an excluded amount cannot be the subject of a payment claim under the Act, it may still be resolved in accordance with any dispute resolution provisions in the contract or by going to court.

See Fact Sheet 4: Claimable variations and excluded amounts

Top of page

What happens if I don't pay the claimed amount?

The Act requires a respondent who receives a valid payment claim to pay the amount claimed in full by the due date or give the claimant a payment schedule within 10 days.  If the respondent does not do one of these things within the required time, they become liable for the amount claimed.

The claimant may apply for adjudication or go to court to recover the unpaid amount.  The claimant may also exercise a lien in respect of the unpaid amount over any unfixed plant or materials they have supplied to you for use in connection with carrying out construction work under the contract.  They may also suspend works, or the supply of goods and services under the contract, until the amount payable has been paid. 

A 'paid when paid' provision in a construction contract has no effect.  The claimant cannot be required to wait until the respondent is paid by someone else under another contract. 

The claimant also has these options if you

  • Provide a payment schedule and the scheduled amount is less than the claimed amount, or
  • Provide a payment schedule but do not pay the scheduled amount by the due date.

See Fact Sheet 11: If the respondent doesn't pay, and Fact Sheet 12: Lien over unfixed plant and materials

Top of page

What happens if I don't submit a payment schedule?

If you do not provide a payment schedule on time you will become liable to pay the full amount claimed.  Interest may be payable on the unpaid claimed amount.  The claimant may go to court to recover the full amount as a debt or apply for adjudication. 

The claimant is entitled to suspend work or cease supplying related goods and services under the contract until the amount payable has been paid.  If the claimant exercises this right in accordance with the Act they will not be liable for any loss or expense you suffer as a consequence of the suspension. 

The claimant also has the right to exercise a lien in respect of the unpaid amount over any unfixed plant or materials that they have provided in connection with carrying out construction work.

For more information see Fact Sheet 8: Responding to a payment claim and Fact Sheet 12: Lien over unfixed plant and materials

Top of page

What should be included in a payment schedule?

A payment schedule is the respondent's reply to a payment claim when they do not agree to pay the amount claimed by the due date.  It states how much the respondent will pay the claimant and why.  To be valid the payment schedule must:

  • Identify the payment claim to which the payment schedule relates.
  • Identify the amount (if any) that the respondent proposes to pay ('the scheduled amount').
  • Provide any reason why the scheduled amount is less than the claimed amount, including any reason why the respondent may be withholding payment.
  • Identify any amount of the claim that the respondent alleges is an excluded amount.

sample payment schedule is available.  It can be filled in or used as a guide.

Top of page

How do I serve a payment schedule?

The respondent has 10 days after receiving the payment claim to serve the payment schedule on the claimant, unless the contract allows less time. 

A document may be served under the Act in one of the following ways:

  1. Delivered in person. It is 'served' when the respondent receives it.
  2. Lodged during business hours at the respondent's ordinary place of business. It is 'served' when it is received at that address.
  3. Sent by post to the respondent's ordinary place of business. It is 'served' 2 business days after the day it is posted.
  4. Faxed to the respondent's ordinary place of business. It is 'served' at the time it is received unless it is received after 4pm. If it is received after 4pm, it is taken to have been 'served' on the next business day.

Provided in any other manner specified in the contract.

See Fact Sheet 8: Responding to a payment claim

Top of page

What if the claimant disputes the payment schedule?

If the claimant has served a valid payment claim and you provide a payment schedule which shows that the amount that you propose to pay (the 'scheduled amount') is less than the amount claimed on the payment claim (the 'claimed amount'), the claimant can apply for adjudication.  The claimant has 10 business days after receiving the payment schedule to apply. 

The claimant applies for adjudication by lodging an application with an Authorised Nominating Authority (ANA) such as BAV. An ANA is an organisation authorised by the Building Commission to nominate adjudicators under the Act.

See Fact Sheet 5: Applying for adjudication

Top of page

When can a claimant apply for adjudication?

The claimant may apply for adjudication when they have served a payment claim on a respondent under the Act and, as a result, one of the following circumstances has arisen.

  • The respondent has provided a payment schedule which shows that the amount that they propose to pay (the 'scheduled amount') is less than the amount claimed on the payment claim (the 'claimed amount').   
  • The respondent provides a payment schedule but does not pay any or all of the 'scheduled amount' when it is due.   
  • The respondent fails to provide a payment schedule or pay any or all of the 'claimed amount' when it is due.

 See Fact Sheet 11: If the respondent doesn't pay

See also FAQ 'What happens if I don't pay the claimed amount'

Top of page

What do I do if I receive an adjudication application?

If you receive an adjudication application you may provide an 'adjudication response' if you have previously provided a payment schedule in accordance with the Act.  An adjudication response is the respondent's reply to the claimant's adjudication application. 

Your adjudication response must be lodged with the nominated adjudicator 5 business days after receiving a copy of the adjudication application from the claimant, or 2 business days after receiving notice of an adjudicator's acceptance of the application - whichever is later.  A copy of the response, including any attachments, must also be served on the claimant.

See Fact Sheet 10: Responding to an adjudication application

Top of page

What should be included in an Adjudication Response?

An adjudication response is not required to be in any particular form.  To be valid, an adjudication response must:

  • Identify the adjudication application to which it relates
  • Include the name and address of any relevant principal of the respondent
  • Include the name and address of any other person who the respondent knows has a financial or contractual interest in the matters that are the subject of the adjudication application and
  • Identify any amount of the payment claim that the respondent alleges is an excluded amount.

The adjudication response may contain any relevant submissions the respondent chooses to include.

The Building Commission has prepared a sample form which can be filled in or used as a guide. 

See Fact Sheet 10: Responding to an adjudication application

Top of page

What happens if I don't pay an adjudicated amount?

If the payment dispute is referred to an adjudicator, the adjudicator may determine that the respondent must pay an amount to the claimant (the 'adjudicated amount').  If the respondent fails to pay the adjudicated amount on time, the claimant has the following options.

  • Go to court to recover the adjudicated amount

The claimant can recover the adjudicated amount by filing an adjudication certificate and supporting affidavit in the appropriate court.  The adjudication certificate is available from the Authorised Nominating Authority (ANA) to which the adjudication application was made.  It sets out the names of the parties, the amount payable and the date on which it was due to be paid.  The affidavit attests to the fact that the amount is still outstanding.  The adjudicated amount will become a judgment debt, which is enforceable in the same way as any court judgment.  Fees will be payable to the ANA for the adjudication certificate and to the court for registration of the debt. 

  • Recovery from the principal

If the adjudicated amount is for work, goods or services that are incidental to or part of a contract between the respondent and a third party (the principal), the claimant may recover the adjudicated amount from the principal.  This option is not available in relation to a domestic building contract with a building owner, unless the building owner is in the business of building residences.

To recover payment from the principal, the claimant must obtain an order from a court for the adjudicated amount.  The court will issue a Debt Certificate, which must be served on the principal with a Notice of Claim.  The Notice of Claim and Debt Certificate must be in the prescribed forms, which are set out in the Building and Construction Industry Security of Payment Regulations 2003

  • Other actions

Until the debt is paid, the claimant retains the right to suspend work or the supply of goods and services and to exercise a lien over unfixed plant and materials.

See Fact Sheet 11: If the respondent doesn't pay

Top of page

Can I ask for review of the adjudication?

The adjudication process established by the Act is intended to provide a quick and inexpensive way to resolve payment disputes arising under construction contracts.  In support of this aim, adjudicator's decisions are generally not reviewable.  However, an adjudicator's determination may be reviewed by another adjudicator in limited circumstances.  This process is available to both parties.

A determination may be reviewed only where the contract was entered on or after 30 March 2007, and the adjudicated amount exceeds $100,000.

The grounds for review are limited.  A respondent may seek review of a determination on the ground that the adjudicator wrongly included in the determination amounts which are 'excluded amounts'.  A claimant may seek review of a determination on the ground that the adjudicator failed to include in the determination an amount or amounts wrongly identified as 'excluded amounts'.

See Fact Sheet 7: Adjudication review

Top of page

How do I apply for adjudication review?

The application must be made to the Authorised Nominating Authority (ANA) to which the adjudication application was made.  Applicants (whether respondent or claimant) have 5 business days after receiving the adjudication determination to apply for review.

There is no prescribed form for an adjudication review application.  It must be in writing and must be accompanied by the ANA's application fee (if any). 

A respondent may for review only if they have taken all of the following steps

  • They provided the claimant with a valid payment schedule on time.
  • They identified an 'excluded amount' in their payment schedule or adjudication response.
  • They have paid the claimant all the undisputed amounts determined by the adjudicator.
  • They have paid any amounts they have identified as 'excluded amounts' into a designated trust account, and given the claimant details of the account.

See Fact Sheet 7: Adjudication review

Top of page

Can a claimant suspend work?

The claimant has a right to suspend works, or supply of goods and services to the respondent until the amount payable has been paid.  The respondent must be given 3 business days' written notice of the suspension.  The notice must state that it is made under the Act.  A claimant who exercises this right in accordance with the Act is not liable for any consequential loss or expense suffered by the respondent.

Top of page

When can an adjudicated amount be recovered from the contract principal?

If the adjudicated amount is for work, goods or services that are incidental to or part of a contract between the respondent and a third party (the principal), the claimant may recover the adjudicated amount from the principal.  This option is not available where the principal is a homeowner who lives in, or intends to live in, a house where the work is being carried out. 

To recover payment from the principal, the claimant must obtain an order from a court for the adjudicated amount.  The court will issue a Debt Certificate, which must be served on the principal with a Notice of Claim.  The Notice of Claim and Debt Certificate must be in the prescribed forms, which are set out in the Building and Construction Industry Security of Payment Regulations 2003

Service of the Notice of Claim assigns to the claimant the debt owed by the principal to the respondent.  The principal must then pay the claimant the money that the principal owes the respondent until the debt is discharged or the principal is no longer required to pay the respondent.  If the principal fails to make the payment as required, the claimant may sue for recovery of the debt.

Top of page

What is a 'relevant principal'?

The adjudicator must notify any relevant principal of an adjudication application.

A relevant principal is any person who has engaged the respondent under a contract to provide construction work, goods or services, if the work that the claimant has done or the goods or services that the claimant has supplied under contract to the respondent is, or is part of or incidental to, the construction work, goods or services that the respondent was engaged to carry out or supply. 

This does not include the principal in a domestic building contract to which the Act doesn't apply. For more information about this exemption See Fact Sheet 1: The Security of Payment scheme

Top of page

 

 

Building Adjudication Victoria Inc.

Level 3, 296 Collins St.
Melbourne Vic. 3000

t : 03 9663 4722
f : 03 9663 4799
bav @ rodlaw.com.au